Difference between revisions of "F16: Autonomous Nautical System"
(→Parts List & Cost) |
(→Schedule) |
||
Line 35: | Line 35: | ||
! scope="col"| Week# | ! scope="col"| Week# | ||
! scope="col"| Date | ! scope="col"| Date | ||
− | ! scope="col"| | + | ! scope="col"| Tasks |
! scope="col"| Actual | ! scope="col"| Actual | ||
|- | |- | ||
! scope="row"| 1 | ! scope="row"| 1 | ||
| 10/8 | | 10/8 | ||
− | | | + | | Decide on boat hull based on the amount of devices |
− | | Completed | + | we planned to us. |
− | |} | + | Purchased motor, servo, and battery accordingly |
+ | | Completed | ||
+ | Brushed DC motor powered by Electronic | ||
+ | Speed controller was purchased. | ||
+ | |- | ||
+ | ! scope="row"| 2 | ||
+ | | 11/4 | ||
+ | | Intercept the pwm signals issued by a remote | ||
+ | control for steering and speed throttling. Decode | ||
+ | these signals over time to identify which values produce | ||
+ | what kind of effect to the driving system. | ||
+ | | Completed | ||
+ | Using a logic analyzer did not work the way we planned | ||
+ | An oscilloscope was used but only to prove that this | ||
+ | was not necessary since the motor and servo reacts to | ||
+ | PWM as any other motor or servo. | ||
+ | |- | ||
+ | ! scope="row"| 3 | ||
+ | | 11/25 | ||
+ | | Make separate compass, gps, and pwm tasks | ||
+ | | Completed | ||
+ | These tasks are a simple tasks demoing the functionality | ||
+ | |- | ||
+ | ! scope="row"| 4 | ||
+ | | 12/02 | ||
+ | | Link separate task outputs together using navigation task. | ||
+ | | Completed | ||
+ | Debug the steering and motor control commands issued | ||
+ | by the state of the navigation task state machine. | ||
+ | |- | ||
+ | ! scope="row"| 5 | ||
+ | | 12/16 | ||
+ | | Revise gps task to give only needed information and use | ||
+ | all task outputs in the navigation task | ||
+ | | Completed | ||
+ | Buggy and needs to check for invalid information using checksum | ||
+ | |- | ||
+ | ! scope="row"| 6 | ||
+ | | 12/20 | ||
+ | | Update the wiki page | ||
+ | | Completed | ||
+ | Clean up exceptions in the land demo program | ||
+ | |- | ||
+ | } | ||
== Parts List & Cost == | == Parts List & Cost == |
Revision as of 00:27, 21 December 2016
Contents
Grading Criteria
- How well is Software & Hardware Design described?
- How well can this report be used to reproduce this project?
- Code Quality
- Overall Report Quality:
- Software Block Diagrams
- Hardware Block Diagrams
- Schematic Quality
- Quality of technical challenges and solutions adopted.
Autonomous Nautical Systems for Ocean Transit and Survey (ANSOTAS)
Abstract
Constructing an autonomous navigation system responsive to GPS and Tilt Compass feedback to form and track trajectories to a given location. Low power, and observant system.
Objectives & Introduction
Show list of your objectives. This section includes the high level details of your project. You can write about the various sensors or peripherals you used to get your project completed.
Team Members & Responsibilities
- Angel Hernandez-Perez
- Fayek Wahhab
- Abraham Carrillo
Schedule
Show a simple table or figures that show your scheduled as planned before you started working on the project. Then in another table column, write down the actual schedule so that readers can see the planned vs. actual goals. The point of the schedule is for readers to assess how to pace themselves if they are doing a similar project.
Week# | Date | Tasks | Actual |
---|---|---|---|
1 | 10/8 | Decide on boat hull based on the amount of devices
we planned to us. Purchased motor, servo, and battery accordingly |
Completed
Brushed DC motor powered by Electronic Speed controller was purchased. |
2 | 11/4 | Intercept the pwm signals issued by a remote
control for steering and speed throttling. Decode these signals over time to identify which values produce what kind of effect to the driving system. |
Completed
Using a logic analyzer did not work the way we planned An oscilloscope was used but only to prove that this was not necessary since the motor and servo reacts to PWM as any other motor or servo. |
3 | 11/25 | Make separate compass, gps, and pwm tasks | Completed
These tasks are a simple tasks demoing the functionality |
4 | 12/02 | Link separate task outputs together using navigation task. | Completed
Debug the steering and motor control commands issued by the state of the navigation task state machine. |
5 | 12/16 | Revise gps task to give only needed information and use
all task outputs in the navigation task |
Completed
Buggy and needs to check for invalid information using checksum |
6 | 12/20 | Update the wiki page | Completed
Clean up exceptions in the land demo program |